Planning
Assistance with your final product selections, prepare the construction agreement that includes scopes of work, begin/end dates, payment terms, licensing and insurance information. Order products & materials, schedule trade partners, and apply for the building permits.
Preparation
Deliver dumpster (placed on ground protection) and portable toilet for our workers. Surface and floor protection includes roll-out mats, draped plastic over furniture, dust containments, designated areas for tools and materials.
Demolition
Remove and discard contents per space including accesssories, vanity, toilet, tub/shower, first layer of floor covering, and first layer of wall covering in shower alcove.
HVAC (50 – 70) cfm
Install an exhaust fan vented to the exterior through a sidewall or soffit.
Plumbing Fixtures (3)
Install drain and water supply lines, new shutoff valves, p-traps, fixtures, and test for leaks for a shower, vanity and toilet.
Electrical Devices (4)
Install wiring to 4 devices (includes switches, outlets and surface lighting).
Insulation
Install fiberglass batt type insulation in exterior walls (R11/13/15) & ceilings (R19/30/38).
Drywall
Installation of mold/mildew resistant drywall, tape, compound, sand and prepare your walls and ceiling for painting.
Tile: Main Floor (40sf)
Floor areas receive anti-fracture membrane to guard against cracking. Tile setters will then install ceramic or porcelain tiles set in the determined pattern. Grout and seal any joints.
Finishes; Trim/Molding (8) Lf.
Carpenters will install new molding up to 8 Lf. We will also be installing your towel bar, toilet paper dispenser, hand towel ring, shower rod, and vanity mirror.